Orgill Warehouse | Rome, NY

Smith Site Development was awarded the Civil Site package for the project. The Warehouse facility required site demolition, asphalt milling, cut and fill with dynamic compaction requirements.

  • Install Building Pad & Paving Subbase Material

  • Install Drainage Swales and Driving Lanes

  • Install Concrete Curbs & Sidewalk

  • Install Dolly Pads & Concrete Aprons

  • Paved Employee & Trailer Parking Lots

  • Finish Grading

    • Place Topsoil

    • Seed & Mulch

    • ADA Compliant Striping

    • Landscaping

Scope of Work:

  • Erosion Control Measures

  • Clearing and Grubbing

  • Install Bio Retention Basins

  • Mass Excavation – 350,000 Cubic Yards

  • Underground Utilities

    • Stormwater

    • Sanitary Sewer

    • Fire Loop

    • Domestic Water

    • Site Electric

    • Site Natural Gas