Orgill Warehouse | Rome, NY
Smith Site Development was awarded the Civil Site package for the project. The Warehouse facility required site demolition, asphalt milling, cut and fill with dynamic compaction requirements.
Install Building Pad & Paving Subbase Material
Install Drainage Swales and Driving Lanes
Install Concrete Curbs & Sidewalk
Install Dolly Pads & Concrete Aprons
Paved Employee & Trailer Parking Lots
Finish Grading
Place Topsoil
Seed & Mulch
ADA Compliant Striping
Landscaping
Scope of Work:
Erosion Control Measures
Clearing and Grubbing
Install Bio Retention Basins
Mass Excavation – 350,000 Cubic Yards
Underground Utilities
Stormwater
Sanitary Sewer
Fire Loop
Domestic Water
Site Electric
Site Natural Gas